Hyperscale AI Data Center Transit Corridor Guide
Highway routing, bridge weight limits, overhead wire lifting schedules, and police escort curfews for delivering 2MW+ packaged backup generators, 200MVA substation transformers, and modular chiller plants to AI mega-campuses.
Select AI Data Center Transit Corridor
Review state DOT superload bridge limits, overhead wire clearances, curfews, and police escort details.
Detailed Route Alignment & Turn Geometry
Departs Dundalk Marine Terminal at the Port of Baltimore onto I-695 West to I-95 South towards Washington D.C. Bypasses Capitol Beltway congestion via Route 200 (ICC) onto I-270 and US-15 South into Loudoun County. Enters Data Center Alley via Route 7 and Route 28 to Waxpool Road / Beaumeade Circle.
Utility Conflicts & Overhead Obstacle Schedule
Overhead fiber optic cables crossing Route 28 are maintained at 18' 2" minimum height. 2 traffic signal mast arms at Loudoun County Parkway are pre-cleared for 15' 8" load passage with bucket truck escort.
Movement Curfews, Time Windows & Jurisdictional Authorities
Permitted Movement Window
21:00 EST – 05:00 EST (Night Superload Convoy)
Strict rush-hour curfew: zero moves between 06:00–09:00 and 15:30–19:00.
Authorizing Jurisdiction
VDOT Northern Region / Loudoun County DOT
Automated VDOT OS/OW superload permit issuance with bridge rating review.
Campus Site Delivery Protocol
Delivery Staging Slot Pre-Booking
Crane pad slot coordinated with site GC to allow immediate trailer offload.