MEGA-SUPERLOAD • TBM CUTTERHEAD • DUAL-WIDE MODULAR HYDRAULIC PLATFORM

250-Ton TBM Cutterhead Dual-Lane Transport Manual

Rigging and transit guidelines for 180 to 350+ metric ton Tunnel Boring Machine cutterheads and drive assemblies: dual-file 16-24 axle line hydraulic modular transporters, tandem crawler crane hook share, night-transit contraflow city routing, and bridge shoring.

01 TBM Dimension & Platform Configuration

LIVE TBM RIGGING • AXLE WEIGHT TELEMETRY BRIDGE FORMULA PERMITTED
Gross Combination Weight (GCW) 356 t 784,800 lbs total weight
Axle Line Load (Average) 9.8 t ≤ 10.5t permit limit
Overall Transport Width 6.2 m 20.3 ft dual-lane footprint
Overhead Height Apex 6.8 m 22.3 ft clearance required
Hydraulic Suspension Group: 4-Point Virtual Iso-Baric Circuit
Prime Mover Traction: 2 x 8x4 Ballasted Heavy Tractors (Push-Pull)
Police Escort Requirement: 4 State Highway Patrol Cruisers (Contraflow Mode)
Max Operating Speed: 12 mph Highway / 5 mph Bridge Straddle
Exspeedite Heavy Haul Superload Engine • AASHTO / Bridge Division CALCULATED LIVE
01

Dual-Wide Side-by-Side Coupling

Standard single-file platform trailers lack the lateral stability polygon for a 12m-17m diameter circular cutterhead. Couplers mechanically join two parallel 3.0m trailers into a 6.2m wide platform, doubling transverse overturning resistance.

02

Tandem Crawler Crane Pick & Roll

Offloading at the deep launch shaft requires dual heavy crawler cranes (750t to 1000t class) sharing the load via engineered equalizer spreader beams, synchronized with radio telemetry load cells to prevent asymmetrical sling overloading.

03

Bridge Girder Straddling & Shoring

Crossing highway bridges with a 350-ton combination demands travel down the exact bridge centerline at 5 mph to equalize moment distribution between main support piers, preventing concentrated deck punching shear stresses.

Standard Operating Procedure: Metropolitan TBM Superload Moves

1. Midnight Rolling Roadblock & Contraflow Highway Routing

Due to the 20-foot transport width and 22-foot overhead height, transport is restricted to 00:00 - 05:00 hours under full police rolling closure. At designated freeway on-ramps and multi-lane intersections, the convoy utilizes wrong-way contraflow lanes to clear low-clearance highway overpass abutments.

2. Overhead Utility Wire & Signal Mast Swivel Coordination

A forward bucket truck crew precedes the convoy by 15 minutes, swinging traffic signal cantilever arms away from travel lanes and elevating municipal trolley bus or telephone lines with non-conductive lifting poles.

3. Sub-Surface Launch Shaft Gantry Hand-Off

Upon reaching the tunnel launch portal, the modular transporter positions directly under a 600-ton hydraulic gantry or twin strand jack tower system. Hydraulic center-hole jacks lift the cutterhead clear of the transport saddles, allowing the empty trailers to roll out prior to vertical lowering.