Inland Railhead to SMR Power Generation Facility Heavy Route Guide
Route surveys, dual-lane SPMT axle loadings, rural bridge structural reinforcements, and utility line lifting protocols for moving factory-fabricated SMR vessels from mainline rail sidings to nuclear islands.
Select SMR Deployment Corridor
Review rail siding transload locations, highway grades, bridge crossing protocols, and police escort details.
Detailed Route Alignment & Turn Geometry
Departs Union Pacific mainline industrial siding south of Kemmerer rail yard. Transits west along US Highway 189 onto Wyoming State Route 233 towards the former Naughton Power Station site. Negotiates a 90-degree intersection onto plant access road requiring dual-operator crab steering on 20-axle SPMT transporter.
Utility Conflicts & Bridge Reinforcement Schedule
Two timber culverts require temporary steel jump bridges placed prior to convoy passage. One 69kV transmission span requires line outage de-energization, coordinated through PacifiCorp dispatch.
Transit Permitting Windows & Jurisdictional Authorities
Permitted Movement Window
09:00 MST – 14:00 MST (Daylight Superload Window)
Dry road pavement conditions only; zero transit during snow, ice, or fog advisory.
Authorizing Jurisdiction
WYDOT District 3 / Lincoln County Commission
Superload Class IX permit with structural bridge engineering endorsement.
Nuclear Chain of Custody
NRC 10 CFR Part 73 Physical Security Convoy
Real-time tamper telemetry and armed security vehicle leading and trailing.