SUNZIA • TRANSWEST EXPRESS • GRAIN BELT EXPRESS • MULTI-STATE SUPERLOAD PERMITS
Deep Grid Interconnection Transmission Corridor Superload Route Guide
High-tonnage route clearances, bridge bypass engineering, Class 1 rail transload sidings, and utility line lift orchestration for moving 1,200,000 lb converter station superloads across key HVDC energy corridors.
SunZia Southwest: Corona NM East to Pinal County AZ West
550 MILES • 3,000 MWConnecting Pattern Energy wind generation in Torrance & Lincoln Counties, New Mexico, across the Rio Grande basin and southern Arizona desert to the Salt River Project (SRP) transmission nexus in Pinal County.
Origin Rail Transload
BNSF Belen Siding (NM)
Choke Point
Rio Grande Bridge US-380
Trailer Platform
24-Axle Girder Bridge
Lead DOT Authority
NMDOT / ADOT Joint Superload
Critical Engineering Obstacles & Bypass Protocols
MP 042:
Belen Transload → US-60 Continental Elevation Incline
Dual 650HP Prime Movers required in push-pull setup for 6.2% grade over Abo Pass. Automated hydraulic suspension steering on 12-axle rear dolly.
MP 188:
Rio Grande River Crossing (Socorro County, NM)
AASHTO bridge rating structural analysis requires centerline crawl at ≤5 MPH with zero adjacent traffic and beam span deflections laser-monitored.
MP 340:
Peloncillo Mountains State Line Crossing (NM → AZ)
Overhead 69kV transmission crossing requires electric utility line de-energization and lift bucket truck escort across I-10 bypass frontage.
Request Corridor Superload Clearance
Coordinate route engineering, bridge stress simulations, and multi-state DOT permits with Exspeedite Heavy Transport Division.
Compliance Mandate:
• AASHTO LRFR bridge analysis with >1.30 rating factor.
• Continuous GPS electronic permit logging.
• Two law enforcement escorts per state jurisdiction.